| NDT.net - July 2000, Vol. 5 No. 07 |
The size of each gap, if any, between the demand for and the supply of qualified NDE personnel will be determined by calculating differences between the demand and supply curves for each task for each year through the year 2010. Survey information will also be collected, analyzed and interpreted to help define the types of interventions that will be needed to close the anticipated gaps between the demand and supply curves. Study instruments and procedures will be reviewed by the NDE Workforce Advisory Panel established to guide the study, and revised accordingly, at critical points in the project.
The study approach is illustrated in Figure 1.
![]() Fig 1: Project Plan |
| TABLE 1 NDE Tasks Performed for In-Service Inspections of Nuclear Power Plants | |
| 1. | Eddy-current examination of heat-exchanger tubing |
| 2. | Eddy-current examination of steam-generator tubing |
| 3. | Leak testing of containment, bellows, airlocks and/or seals |
| 4. | Leak testing of pressure vessels, pressurizers, steam generators, heat exchangers, piping, pumps and/or valves |
| 5. | Surface inspection of containment welds of dissimilar metals |
| 6. | Surface inspection of piping welds, weld overlays, pressure vessels, nozzles, bolting, control-rod housings and/or welded attachments |
| 7. | Surface inspection of reactor-pump flywheels |
| 8. | Surface inspection of turbines |
| 9. | Ultrasonic inspection of piping (susceptible to IGSCC) and/or weld overlays |
| 10. | Ultrasonic inspection of piping welds, pressure vessels, nozzles, bolting, control-rod housings and/or welded attachments |
| 11. | Ultrasonic inspection of reactor pressure vessels |
| 12. | Ultrasonic inspection of reactor-pump flywheels |
| 13. | Ultrasonic inspection of turbines |
| 14. | Ultrasonic measurement of piping and/or containment-vessel wall thickness |
| 15. | Visual inspection of concrete components and associated tensioning systems |
| 16. | Visual inspection of containment vessels and associated welds, surfaces, venting, seals and/or bolting |
| 17. | Visual inspection of reactor pressure-vessel internals |
| 18. | Visual inspection of supports for piping and/or other components |
| 19. | Visual inspection of welds |
The results of the first-phase effort will be a set of NDE personnel demand curves (or tables), one for each level of personnel qualification for each NDE task. For the years beyond 1999, each curve will be bounded by estimated upper and lower limits on anticipated requirements.
In the second phase of the study, the remaining nuclear power plants will be surveyed to obtain their demand curves. An NDE manager or planner at each plant will be provided with the curves obtained in the first phase, to review and verify each as appropriate for that plant or, if not, to modify each to fit the expectations of the plant. Numbers will then be averaged over the sample of plants to obtain composite (typical) NDE personnel demand curves for a nuclear plant. If significant differences are found among types and sizes of plants, a family of composite curves will be developed.
This instrument will be reviewed again by the NDE Workforce Advisory Panel and by a sample of NDE plant managers and planners, and revised accordingly, prior to the start of the data-collection effort.
Survey Method
The survey will be conducted by means of computer-assisted, telephone interviews, in which the interviewer records responses on the computer, and the computer goes to the next question based on the previous response. Survey results, along with those of the Sources survey, will aid in the construction of NDE personnel supply curves. In addition, the survey is designed to explore issues that might affect individual decisions to leave or stay in the NDE profession, providing insights relative to interventions that might be employed to assure NDE workforce availability for the nuclear power industry. At the core of this survey are the following questions asked about each of the 21 NDE tasks performed in nuclear power plants.
Survey Tasks
Conducting the Personnel survey will consist of completing the following project tasks.
| © NDT.net - info@ndt.net | |Top| |