![]() ·Table of Contents ·Industrial Plants and Structures | The automatic performance of the repetition tests of pressure bottles with AEP. Tscheliesnig, G. Lackner (TÜV Austria);W. Hermeling (Messer Austria) Contact |
Furthermore the situation of the normal testing department in the gas supply companies don't allow any change in the testing concept. The erection of a new test- and filling station allows a complete new concept, which could be established during the design of the testing house.
Upon the experience two main defects occur in pressure equipments, for the transportation and storage of compressed gas, pressure bottles:
To answer the 3 main questions a lot of different tests have to be carried out on pressure bottles
The bottles would be tested till to their burst pressure and the AE data set were collected with two sensors, one on each end of the bottles.
Based on previous investigations we and other AE user found out, that the worst case for the AE are the fatigue crack compared to all other possible defects in the bottles including corrosion [2,3]. Therefore most of the tests were carried out with such defects. For this type of defects we have to take into account, that such defects don't produce an increase of the AE-activity or, that this information occurs to late, because the defect is still critical. But in contrary we can expect only few high amplitude AE signals [4].
We produced gas storage bottles with different notches. After the establishment of the loading (accessories and pressurisation rate) on normal, defect free pressure bottles, the bottles with the notches have been cycled till to the crack initiation. The predicted burst pressure should be in the range between the design and the test pressure.
Fig 1: Test jig for the gas pressure bottles |
Fig 2: Burst test on a pressure bottle with artificial introduced fatigue crack
|
Fig 3: Stop criteria for artificial injured bottles |
The stop- and rejection criteria for the defective pressure bottles became established and validated [5]. The results showed, that it is an absolute necessity to locate the defects, as a very important filter criteria against other noise-sources within this pressure bottles (picture 3). For this reason further tests with during the visual examination rejected bottles and such with support rings were performed. The results showed different location and characteristic, even for the stop criteria, but could be distinguished easily one from the other.
Further tests on corroded bottles could demonstrate the ability of the detection of such defects very easily compared to the fatigue cracks (picture 4 and 5).
Fig 4: Corrosion between cylinder and support ring of a pressure bottle
|
Fig 5a:
|
Fig 5b: |
| Fig 5: Pressure test on a pressure bottle with severe corrosion between cylinder and | ||
In the semi-automatically test bench 12 pressure bottles shall be tested parallel with the storage medium. The pressurisation will be done with the pre-defined rate of 5 bar.min-1 from 60 % till to 130 % of the design pressure. During this time the AE signals were acquired and evaluated directly by the AE-equipment without any interference by the test personnel itself. If the tests run properly no further action become necessary. In the case ,if any of the tested bottles reach the stop criteria, the pressurisation will be stopped immediately by the host-computer and a safety relief valve will be opened and all bottles will be de-pressurised.
After reaching the safe condition the test-personnel enter the bunker and take out the defective bottle and replace it in the test bench by a new one. The test can be continued.
During the pressurisation of the bottles in the second chamber 12 further bottles will be equipped and the proper action of the equipment will be checked. Only if the position of the sensor and the sensitivity is correct, the host computer gives the next test phase free.
The test pressure will be held for a period of 10 min and afterwards the filling will be reduced down to the normal working pressure and no further actions, like emptying, draining and filling with the stock product are necessary.
The bottles can go into service till to the next necessary repetition tests.
The stop and rejection criteria was established during the test phase and shall be improved permanently according the gained result and experiences. At the beginning the criteria have to be established very conservative and at the safe side. With more and more experience the rules can be defined more accurate.
You have to take into account, that the personnel cannot interfere into the test-procedure and every step of it can only be started, if the forward action was accepted by the host-computer. Changes of the procedure and much more also from the stop- and rejection criteria have to be done by the responsible man and have to be adopted by the responsible test agency.
During such a run in phase the complete AE equipment and all actions have to be checked.
All these actions show clearly that the complete logistic has to be changed compared to the normal conventional testing procedure, because this test is also now the last point of the complete testing and filling procedure.
The TÜV Austria got the duty to develop the procedure for the tests and to establish safe stop- and rejection criteria. For this aim a lot of pre-tests had been performed. During these pre-tests also the requirements for the AE equipment and specially the adjoining soft-ware were determined.
Based on the results of this project the AE testing could be implemented into the logistic of normal repetition test of pressure equipments for the gas storage and transportation, with the result that the test is more
| © AIPnD , created by NDT.net | |Home| |Top| |