Figure 1 Weld Zones
Recently incorporated "mapping" or colour B-scans, to characterize porosity and geometric origins of signals was also used. A significant addition to the techniques was time of flight diffraction (TOFD). These two enhancements provided the much needed confidence to detect off angle and volumetric defects. TOFD also added the ability to improve defect sizing and assessment of mismatch (high-low). However, the great advantage of TOFD to detect defects near the inside surface is reduced when pipe mismatch occurs. Also, due to the ring time of the lateral wave the upper 4-5 mm cannot be thoroughly inspected by TOFD. For these reasons standard pulse-echo techniques are retained.
|
From Figure 2 it will be noted that the root region of the weld is inspected with two angles. Normal single Vee bevels usually use a small vertical land but pipe ovalities make this configuration the ideal situation not the norm. The actual land may vary plus or minus 1mm from its nominal 1mm height. Using 60° refracted angles for inspection of corner reflectors provides weak signals so this region is better inspected using 70° beams for detection of incomplete penetration or vertically oriented cracking. However, if the land is not present due to pipe ovality, nonfusion or nonvertical cracking is more likely to be detected by the 60° beam.
Amplitude response for the pulse echo probes is set to provide a gated signal to 80% Full Screen Height from a 2mm diameter flat bottom hole. Target holes are positioned on a calibration piece made from a section of pipe such that the flat bottom aligns parallel to the theoretical weld preparation face with respect to the weld centreline.
| Figure 2 Beam Paths
| | A further enhancement to the technique is the incorporation of four probes oriented to detect transverse indications by an angulated pitch-catch arrangement. Placement for optimum detection is difficult and care must be taken to ensure near surface geometric signals do not cause false alarms.
Figure 3 illustrates placement of the inspection head on the calibration standard and on the pipe using the guide band positioned by the technician.
| Figure 3 Scanner Placement
Placement on calibration standard (left) and on pipe (right)
|
|
|
Display of Data
Addition of the extra pulse-echo probes for transverse indications does not add greatly to the data collected as compared to the previous techniques for mechanized weld inspections. Only amplitude and transit-time in a gate are stored for the transverse looking probes. This amounts to just four or five kilobytes of information. However, TOFD data is somewhat more memory intensive as waveforms need to be collected. TOFD information added to the other multichannel information increases the compressed file size from about 1 Mbytes to about 2 Mbytes per weld (typical for 1.067m (42") diameter 10.6mm wall pipe).
Increasing the amount of information provides the operator with a better opportunity to make accurate evaluations. However, the speed of inspection cannot be compromised by slower acquisition speeds nor can the inspection time be increased by the operator spending more time sorting through more data. To prevent more useful information from becoming a limiting factor, instead of an enhancement, an effective display of information was developed.
All information is displayed using colour enhancements, symmetry and scrolling features that ensure the operator can comfortably view all data collected and still be assured of not missing significant indications.
TOFD information lends itself to digital signal processing after data is acquired. The TOFD display demonstrated by RTD is equipped with several useful features to aid in flaw analysis and enhancement. TOFD utilities include;
- linearization of cursors for accurate sizing
- straightening to allow alignment of the lateral wave and preserve a straight entry surface (this is required where mechanical movement of the scanning head causes a slight probe movement)
- filtering to enhance valid flaw signals and reduce noise signals (increasing signal to noise ratio)
|
The ability of TOFD and the low amplitude B-scan mapping to assist in evaluation can be seen in Figure 4. An example of the monitor display of a "wagon-wheel" defect (parallel elongated slag inclusions) illustrates the ease with which an operator can now make evaluations. The upstream (left side) of the Zone 4 strip charts and B-scan mapping show only weak signals originating from the flaw where partial remelting has reduced the flaw volume but the downstream side indicates a strong reflection from Zone 3.
Highlighting the transit-time (grey shading on the analogue-type strip chart) by changing its colour to red, allows the operator to move to areas exceeding the evaluation threshold for a distance exceeding the minimum acceptance length of a defect (also shown in Figure 4).
The RotoTOFD option can be configured to be scrolled on one side of the display as in Figure 4 or a simple toggling can zoom the TOFD image to about four and a half times the normal size and position it mid screen between the strip chart image to facilitate quick sizing by better display resolution of the waveform. Figure 5 allows the operator to determine that the defect in question initially occurs 3.5mm from the ID surface. (Figures 4 & 5 are from scans of test welds in 16.0mm wall).
|
Figure 4: Defect seen by TOFD, Analogue-type strip charts and B-scan mapping
Figure 5: Zoomed TOFD Image
|
Code Developments Required
The single greatest advantage of TOFD is its ability to provide accurate vertical extent of a defect. Accuracies of 0.1 to 0.2 mm are possible using some TOFD techniques. This could greatly extend allowable defect lengths in Engineering Critical Assessment calculations when applying the code. In the trials on the 42" diameter pipe no ECA had been developed but reasonable confidence was had that a minimum defect height of 2mm could be assessed. This limit would apply to the pulse-echo channels for the near OD and for the ID where significant mismatch would be present, however, much finer vertical resolution could be had for TOFD detected indications.
Codes such as API 1104, API RP2X, CSA Z184 and ISO/CSA Z662 provide "workmanship" acceptance criteria for radiography. Although provisions are made in these codes for ECA's to be used to establish longer defect lengths, few companies elect to use them or their customers do not permit the use of an ECA but insist on workmanship criteria because the radiographic acceptance is the only thing they feel comfortable or familiar with. Some rationalize workmanship is "more stringent" (so they think). However, it is well understood by most engineers (4) that repairing a small defect can be more detrimental to the strength of the metal than leaving the benign flaw in the weld. The repair can introduce other non-detected flaws, and the added heat input extends the heat affected zone thereby locally reducing the fracture toughness of the metal.
Table 1 shows a comparison of allowable defect lengths for workmanship and a typical ECA using some API 1104 criteria. This shows how the number of repairable indications could be reduced by knowing the maximum vertical extent of a flaw. (All units in Table 1 are in inches).
Table 1
Parameters:
Pipe Diameter: 30.0 in
Wall Thickness: 0.577 in
CTOD Attained: 0.01 in.
Maximum Applied Strain: 0.002 ((100% yield) (inches per inch)
Inspection error: 0.05 (depth measurements)
| Flaw Type | Depth Range | Acceptable Length UT with ECA
| RT Flaw and length |
| Planar Surface flaws | 0.000 in to 0.144 in 0.145 in to 0.289 in
| 12.00 in 2.31 in
| Incomplete penetration
1in |
| Planar buried flaws | 0.000 in to 0.144 in 0.145 in to 0.289 in
| 12.00 in 2.31 in
| Incomplete fusion 1in |
| Slag (Table A-1) | 0.144 in | 2.31 in | Elongated slag 2in Isolated <1/8" wide
0.5in
|
| Unrepaired Burnthrough
(Table A-1) | 0.144 in | 1.15 in | Isolated RT density
greater than pipe 0.25in |
| Arc Burns | 0.063 in | 0.31 in | As directed by company |
Conclusions
Ongoing efforts have provided the increased confidence in the mechanized UT of girth welds to the point where it can now be recommended for application to non-mechanized welding techniques. With more information now collected, including information that can detect off-angle planar and volumetric flaws, evaluations are more reliable for defects intrinsic to the manual welding process.
A review of radiographs versus UT results for the welds tested in the 1997 Canadian demonstration presented impressive statistics. All significant indications identified by radiography were detected by UT. TCPL requires maximum radiographic sensitivity as afforded by Class 1 film used in conjunction with true radial beam X-ray tubes. In spite of this high sensitivity, there were examples of nonfusion detected by UT could not be seen on the high quality X-ray radiographs.
Daily operating costs of mechanized UT that should not be significantly higher than radiography. However, several cost advantages could be realized by using UT. Time of inspection is reduced, process control is possible, vertical sizing is possible, ECA criteria can be applied allowing longer flaws therefore fewer repairs, a single UT crew dedicated to tie-in weld inspection can provide the production capability of two or three radiographic crews and avoid radiation hazards, in tie-in applications results of inspection are available faster so welding crews can be freed up sooner to move on to the next tie-in location.
The system demonstrated was used on production mainline welds, however, it is intended to be used on manually welded tie-in joints in ditches and the potential exists to apply the technique to field fabrication in stations thereby allowing inspection and welding to go on beside one another without the stoppage in production or re-scheduling of inspection required when radiography is used. Tie-in delays of three to four hours for large diameter welds now shot with radiography could be reduced to less than 15 minutes.
The many advantages of UT must be quickly addressed by Codes now dominated by radiographic inspection acceptance criteria. Users (owners and construction companies) should also take the initiative to utilize the combination of Ultrasonic testing with an effective ECA.
Acknowledgments
The authors would like to thank RTD Quality Services Inc. (Canada) for the images provided.
The authors would also like to thank TransCanada Pipelines Ltd. for their ongoing efforts to promote ultrasonic inspection in the pipeline industry.
References
- E.Ginzel & R.Ginzel, B.Gross, M.Hoff, P.Manuel, Developments in Ultrasonic Inspection for Total Inspection of Pipeline Girth Welds, 8th Symposium on Pipeline Research, Houston, Texas, August 1993
- Glover et al, Inspection and Assessment of Mechanized Pipeline Girth Welds, Proceedings: Weldtech 88, London, UK, 1988
- E.Ginzel, Further Developments In Ultrasonic Inspection of Pipeline Girth Welds, UT Online Journal, ../../../index.html, 1996
- R. Denys, Defect Acceptance Level for Ultrasonically Inspected Girth Welds, University of Ghent (Belgium), 1995, unpublished document.
About the authors
| Merv Hoff is the senior NDT
coordinator for TransCanada
Pipelines.
TransCanada Pipelines Ltd.
111 5th Avenue SE
Calgary, Alberta
Canada
T2P 4K5
tel. (403) 267-6401
fax (403) 267-6242
email merv_hoff@tcpl.ca
|
Peter den Boer is manager of
Automated NDT inspections for
RTD Quality Services Inc.
RTD Quality Services Inc.
1431 70 Avenue
Edmonton, Alberta
Canada
T6P 1N5
tel. (403) 440-6600
fax (403) 440-2538
email peter_b@rtdquality.com
|
Ed Ginzel is an independent
consultant with the Materials
Research Institute.
Materials research Institute
368 Lexington Road
Waterloo, Ontario
Canada
N2K 2K2
tel. (519) 886-5071
fax (519) 886-8363
email eginzel@mri.on.ca
|
The Paper was presented on the UTonline Application Workshop in May '97
|Top to this page|
© Copyright 1. May 1997 Rolf Diederichs,
info@ndt.net
/DB:Article /AU:Ginzel_E_A /IN:MRI /CN:CA /CT:UT /CT:weld /ED:1997-05
|