where expertise comes together - since 1996 -

The Largest Open Access Portal of Nondestructive Testing (NDT)

Conference Proceedings, Articles, News, Exhibition, Forum, Network and more

where expertise comes together
- since 1996 -
928 views
Technical Discussions
scottie
scottie
08:50 Mar-04-2008
code case 181, 2359

Can anyone explain to me where lvl II stand now. As the case states all final data interpretation shall be done by a LVL III, what is the pint in having us LVL II on site if we cant sentence the data. Does this mean that we all have to get LVL III to carry on working


    
 
 Reply 
 
mj
mj
01:17 Mar-04-2008
Re: code case 181, 2359
----------- Start Original Message -----------
: Can anyone explain to me where lvl II stand now. As the case states all final data interpretation shall be done by a LVL III, what is the pint in having us LVL II on site if we cant sentence the data. Does this mean that we all have to get LVL III to carry on working
------------ End Original Message ------------

level II can collect the data and make a overall onsite interpretation, but final review and acceptance from Level III. its realy appricated to go for like that way. because 1.high skills required for TOFD interpreation, that a short experiance level II can't do
2. atleast 2 people should interpretate the data (Most of the End client don't know how to interpretate like Radiography


    
 
 Reply 
 
scottie
scottie
01:31 Mar-04-2008
Re: code case 181, 2359
but surely if lvlIII is reviewing, and on one site u may have 5 or more ToFd crews that this will just prolong getting the results, and in answer to the other part i know more lvl II with much more experience than a lvl II so would a better intrepretation or wording be that the final analysis is performed by someone with for example 4 yrs experience

------- Start Original Message -----------
: : Can anyone explain to me where lvl II stand now. As the case states all final data interpretation shall be done by a LVL III, what is the pint in having us LVL II on site if we cant sentence the data. Does this mean that we all have to get LVL III to carry on working
: level II can collect the data and make a overall onsite interpretation, but final review and acceptance from Level III. its realy appricated to go for like that way. because 1.high skills required for TOFD interpreation, that a short experiance level II can't do
: 2. atleast 2 people should interpretate the data (Most of the End client don't know how to interpretate like Radiography
------------ End Original Message ------------




    
 
 Reply 
 
Nigel Armstrong
Engineering, - Specialist services
United Kingdom, Joined Oct 2000, 1096

Nigel Armstrong

Engineering, - Specialist services
United Kingdom,
Joined Oct 2000
1096
02:29 Mar-04-2008
Re: code case 181, 2359
Clause (j) of both Code Case 181 for ASME B31 Code for Pressure Piping and Code Case 2235-9 for ASME BPV Code only calls for REVIEW by a Level III when the data analysis and interpretation has been carried out by a proprly-qualified level II. Earlier in both documents clause (f) states "Only Level II or III personnel shall analyze the data or interpret the results". No restriction is placed on properly-qualified Level II techs. Its a REVIEW only to ensure that all data is present. The following paragraph does give the option of a final interpretation and evaluation by a Level III after initial acquisition and interpretation by a qualified level II. I cannot see many contractors accepting to go down this route.

Pragmatically, I dont think there is any likelihood of all such work going to level III personnel only. GHow about anyone else?


----------- Start Original Message -----------
: Can anyone explain to me where lvl II stand now. As the case states all final data interpretation shall be done by a LVL III, what is the pint in having us LVL II on site if we cant sentence the data. Does this mean that we all have to get LVL III to carry on working
------------ End Original Message ------------




    
 
 Reply 
 
scottie
scottie
03:43 Mar-04-2008
Re: code case 181, 2359
I agree with what you are saying but unfortunately some people that are now supposedly experts and working for plant owners, insist that the final analysis is carried out by a lvl III this has to be addressed by the board at ASME

----------- Start Original Message -----------
: Clause (j) of both Code Case 181 for ASME B31 Code for Pressure Piping and Code Case 2235-9 for ASME BPV Code only calls for REVIEW by a Level III when the data analysis and interpretation has been carried out by a proprly-qualified level II. Earlier in both documents clause (f) states "Only Level II or III personnel shall analyze the data or interpret the results". No restriction is placed on properly-qualified Level II techs. Its a REVIEW only to ensure that all data is present. The following paragraph does give the option of a final interpretation and evaluation by a Level III after initial acquisition and interpretation by a qualified level II. I cannot see many contractors accepting to go down this route.
: Pragmatically, I dont think there is any likelihood of all such work going to level III personnel only. GHow about anyone else?
:
: : Can anyone explain to me where lvl II stand now. As the case states all final data interpretation shall be done by a LVL III, what is the pint in having us LVL II on site if we cant sentence the data. Does this mean that we all have to get LVL III to carry on working
------------ End Original Message ------------




    
 
 Reply 
 

Product Spotlight

Research Center IDEKO develops an ultrasonic train wheel inspection system for CAF

The Basque Research centre IK4-IDEKO has developed a state-of-the-art ultrasonic inspection system f
...
or the train wheel. This system secures a sound condition of train wheels and is thus a significant contribution to rail transport safety. The device was delivered to CAF recently and its use allows the manufacturer to become an approved supplier of rolling stock in Italy, as it meets the demanding homologation standards of this country. \\\\r\\\\n
>

MUSE Mobile Ultrasonic Equipment

The MUSE, a portable ultrasonic imaging system, was developed for in-field inspections of light-weig
...
ht structures. The MUSE consists of a motor-driven manipulator, a water circulation system for the acoustic coupling and a portable ultrasonic flaw detector (USPC 3010). The MUSE provides images of internal defects (A-, B-,C- and D-scan).
>

FD800 Bench Top Flaw Detectors

The bench-top FD800 flaw detector range combines state-of-the-art flaw detection with advanced mater
...
ial thickness capabilities. Designed for use in the laboratory these gauges are the tool you need for all your flaw detecting needs.
>

EKOSCAN Phased Array

In order to always fit your needs, EKOSCAN can manufacture any type of UT transducer, either convent
...
ional or Phased Array. As an ISO 9001: 2015 certified company, EKOSCAN is extremely careful as far a material selection and manufacturing processes are concerned. Our probes guarantee our customers the benefits of latest innovations regarding piezo-composite, backing, impedance adaptation layer, etc. Specific probes for hostile environment: high temperature, high pressure, corrosive environment,etc. Specific probes designed to fit your specific application: optimization of every parameter to guarantee you the best detection.
>

Share...
We use technical and analytics cookies to ensure that we will give you the best experience of our website - More Info
Accept
top
this is debug window