Slimmoon
Slimmoon
17:13 Mar-26-2009
Regarding NCR

Hi..
Who will fill in NCR , Root cause and corrective action . Quality ,or Production for any NC

 
 Reply 
 
Ed T.
Ed T.
02:51 Mar-27-2009
Re: Regarding NCR
In Reply to Slimmoon at 17:13 Mar-26-2009 (Opening).

In my opinion, the NCR should be filled out by the organization's QA/QC Manager or his representative that received the NCR.
It should then be reviewed after corrective action has been performed by the NCR originator and if satisfied, closed out.

 
 Reply 
 
K.Durga Rao
Consultant, - General Manager (Technical)
Asia Power Projects Pvt Ltd, India, Joined May 2009, 3

K.Durga Rao

Consultant, - General Manager (Technical)
Asia Power Projects Pvt Ltd,
India,
Joined May 2009
3
12:29 Mar-27-2009
Re: Regarding NCR
In Reply to Slimmoon at 17:13 Mar-26-2009 (Opening).

In my view it can be done in two ways; (a) If the non conformity was noticed by production department during manufacture of the goods before it was offered for inspection checks, head of that production section had to raise an NCR and that NCR had to be countersigned by the respective quality control engineer of that section. After the non conformity was attended by the production department, this had to be once again countersigned by the respective quality control engineer confirming the conformity and finally this NCR had to be closed by the management reprasentative of Quality control department. (b) If the non-conformity was noticed by the quality control engineer during his inspection, the NCR had to be raised by that quality control engineer and it had to be countersigned by the production dapartment head. Once this non coformity was resolved, the same quality control engineer had to countersign the NCR confirming the conformity and it had to be closed by the management reprasentative of Quality control department.

 
 Reply 
 
S.V.Swamy
Engineering, - Material Testing Inspection & Quality Control
Retired from Nuclear Fuel Complex , India, Joined Feb 2001, 787

S.V.Swamy

Engineering, - Material Testing Inspection & Quality Control
Retired from Nuclear Fuel Complex ,
India,
Joined Feb 2001
787
03:45 Mar-28-2009
Re: Regarding NCR
In Reply to K.Durga Rao at 12:29 Mar-27-2009 .

Dear Durga Rao garu,

Very good advice. Both production and QA/QC are to be involved at all stages of NCR resolution.

Swamy
QA and NDT Expert

 
 Reply 
 
Abbas Bombaywala
NDT Inspector
Free Lance, India, Joined Jul 2007, 92

Abbas Bombaywala

NDT Inspector
Free Lance,
India,
Joined Jul 2007
92
06:54 Mar-29-2009
Re: Regarding NCR
In Reply to Slimmoon at 17:13 Mar-26-2009 (Opening).

Hi Dear All

I Think Design department should also be involved there should be also comments and signature from Design Department that whether it is accepted or if it is affecting some change in Design part of view then he will raise a DCR to client and upon client acceptance of that DCR the NCR will be closed.

With Regards.
Abbas Zoher

 
 Reply 
 

Product Spotlight

NDTkit RT

NDTkit RT, TESTIA's Digital Radiography software The NDTkit product line software for X-ray analysi
...
s. NDTkit RT is a software benefiting from the Ultis kernel which is dedicated to radiographic image analysis. It offers a set of tools and filtering processes to assist RT operators in finding relevant flaws.
>

Surf-X® Array Probe

Introducing the Surf-X family of flexible Eddy Current Array (ECA) probes. Featuring unique multiple
...
coil sets and proprietary X-PROBE technology, Surf-X array probes can quickly and accurately handle a range of inspection applications, from inspecting corrosion or cracking in pipes, pressure vessels, or tanks, to assessing and sizing cracks in raised welds and friction stir welds.
>

AIS229 - Multipurpose Real Time System

Latest standard & automatic real time system developed by Balteau. The AIS229 has been designed to
...
do series inspection in a wide variety of industry. Composed of a shielded cabinet, 5 axis manipulator, x-ray generator and tubehead from 160kV to 225kV, a fl at panel & much more, the AIS229 is most certainly one of the most multipurpose RTR system available on the market.
>

Robotic laser shearography enables 100% inspection of complex, flight-critical composite structures

An article in “Composites World Magazine” showcases Non Destructive Testing of aero-structures
...
with Laser Shearography. Over the years Dantec Dynamics has supplied many solutions for the aerospace industry. Referring to specific customer projects several of these cases are examined to outline the advantages of using Laser Shearography for automated defect detection.
>