SOP approved?

I wonder if anyone can point me in the direction of any spec's that say your SOP/Work Instruction for NDT needs to be approved by a level III (this is for Oil & Gas industry)

Thanks
Malcolm

 
 Reply 
 
anjafo79
NDT Inspector
Norway, Joined Aug 2009, 204

anjafo79

NDT Inspector
Norway,
Joined Aug 2009
204
08:04 Mar-12-2010
Re: SOP approved?
In Reply to Malcolm at 04:27 Mar-12-2010 (Opening).

EN 473 NDT personnel states what level I, II and III operators are allowed to do, most EN procedures refer back to this standard.

I gues SNT-TC-1a states similar things although I do not have a copy.

ASME V states that personnel should be qualified accorinding to SNT-TC-1a / ASNT-CP-189

 
 Reply 
 
Roger Duwe
NDT Inspector, API-510, 570, 653
MISTRAS, USA, Joined Jan 2009, 148

Roger Duwe

NDT Inspector, API-510, 570, 653
MISTRAS,
USA,
Joined Jan 2009
148
22:49 Mar-12-2010
Re: SOP approved?
In Reply to anjafo79 at 08:04 Mar-12-2010 .

SNT-TC1a allows Level II's to inspect to, and Accept/Reject items to specific criteria, in accordance to a written procedure. The written procedure requires approval by a Level III, prior to allowing a Level I or II to implement it. ASME Code makes these same requirements.

It sounds like your SOP/Work Instruction may fall under these requirements. However, if there is a specific NDE Procedure that can be utilized for your SOP/Work Instruction, and that Procedure is approved by a Level III, your individual Work Instructions probably do not require individual approval from a Level III. You would just reference, and work to, the approved NDE Procedure.

 
 Reply 
 
Kevin Bett
Kevin Bett
06:54 Mar-22-2010
Re: SOP approved?
In Reply to Malcolm at 04:27 Mar-12-2010 (Opening).

EN473, ASME V

 
 Reply 
 
Malcolm
Engineering, oil & gas
Indonesia, Joined Feb 2010, 4

Malcolm

Engineering, oil & gas
Indonesia,
Joined Feb 2010
4
09:09 May-21-2010
Re: SOP approved?
In Reply to Roger Duwe at 22:49 Mar-12-2010 .

Roger, I have the latest edition of SNT-TC-1A and on the front cover it clearly says that this is for guidance only and should NOT be used as a strict procedure.

I just got screwed by the local government body who will not give me a permit to work as they cannot read English and also say as per SNT-TC-1A stipul;ates all proceedures need to be approved by a level III. I have about 230 written proceedures and this would just not be possible.

Think it is time I went home..........

Malcolm

 
 Reply 
 
Nigel Armstrong
Engineering, - Specialist services
United Kingdom, Joined Oct 2000, 1096

Nigel Armstrong

Engineering, - Specialist services
United Kingdom,
Joined Oct 2000
1096
09:35 May-22-2010
Re: SOP approved?
In Reply to Malcolm at 09:09 May-21-2010 .

Malcolm

Where SNT-TC-1A is a set of guidelines for an employer to develop its own personnel certification procedure, CP 189 is a standard, ie once agreed all its clauses are mandatory.

CP 189 defines a procedure as "A detailed written instruction for conducting a nondestructive test or certifying personnel. Method procedures shall be approved by the NDT Level III certified in the applicable method." This is subjective though as procedures are necessarily very detailed as to how the test is done in general, but it cannot be written in advance to cover all essential parameters for an unknown component. If the procedure has been verified and approved by an appropriate Level III then individual component test parameters can be raised by the level II.

For obvious reasons many large end users specify CP 189 rather than SNT-TC-1A as it sets out a minimum standard.

You could have a few procedures according to the number of NDT methods you wish to utilise and then addend the different instructions to the relevant procedure. Provided the instructions are written by an appropriately qualified Level II and conform with the procedure they should not require Level III approval.

Hope this helps prevent your premature return home!

 
 Reply 
 
Malcolm
Engineering, oil & gas
Indonesia, Joined Feb 2010, 4

Malcolm

Engineering, oil & gas
Indonesia,
Joined Feb 2010
4
06:18 May-24-2010
Re: SOP approved?
In Reply to Nigel Armstrong at 09:35 May-22-2010 .

Nigel,
The light just switched on in my head.

I will get my MT, PT & UT work instruction approved by a level III and referance all my other WI's back to them.

What a saving..........

Thanks
Malcolm

 
 Reply 
 
Manuel Haces
Director, - Wire rope inspection
Haces Inspección del Noreste and Wire Rope Inspection, Mexico, Joined Jun 2002, 124

Manuel Haces

Director, - Wire rope inspection
Haces Inspección del Noreste and Wire Rope Inspection,
Mexico,
Joined Jun 2002
124
01:27 May-25-2010
Re: SOP approved?
In Reply to Malcolm at 06:18 May-24-2010 .

If anybody have references and instruction material it will be greatly apreciated, I'm also preparing for level III. Thank you in advance.

 
 Reply 
 

Product Spotlight

SONOAIR - air-coupled Phased Array Ultrasonic Inspection System

For highly attenuating materials, the performance of the system is critical. The ultrasonic sensors,
...
the scanning area and the system settings should be flexibly adapted to the test task and the material. These high expectations are met with the new and modular testing system SONOAIR. With the world’s first air-coupled phased-array UT inspection system SONOAIR we developed a technology that works with up to 4 transmitter and receiver channels with freely configurable square wave burst transmitters as wells as low noise receiving amplifiers.
>

Combination of Digital Image Correlation and Thermographic Measurements

The combination of measuring results from the digital image correlation (ARAMIS, DIC) and temperat
...
ure measuring data from infrared cameras permits the simultaneous analysis of the thermal and mechanical behavior of test specimens in the materials and components testing field.
>

UCI Hardness Tester NOVOTEST T-U2

UCI hardness tester NOVOTEST T-U2 is is used for non-destructive hardness testing of: metals and
...
alloys by scales of hardness: Rockwell (HRC), Brinell (HB), Vickers (HV); non-ferrous metals, alloys of iron etc., and using five additional scales for calibration; with tensile strength (Rm) scale determines the tensile strength of carbon steel pearlitic products by automatic recalculation from Brinell (HB) hardness scale.
>

MIZ®-21C: Truly Affordable Eddy Current Handheld with Surface Array Capability

Introducing MIZ-21C, the first truly affordable handheld eddy current instrument with surface array
...
capabilities. MIZ-21C can deliver fast, accurate inspections in demanding NDT applications including aerospace, oil and gas, manufacturing, and power generation. The surface array solution can reduce inspection time by up to 95% compared to traditional handheld pencil probes. The ergonomic design, long battery life, and intuitive touchscreen mean you can inspect more areas faster than ever without fatigue.
>

Share...
We use technical and analytics cookies to ensure that we will give you the best experience of our website - More Info
Accept
top
this is debug window